the best news ever came for the farmers of Gujarat, know what the energy minister said?
Gujarat Energy Minister Saurabh Patel has made an important announcement today. Good news for farmers. Let's find out what he has to say. o The best news so far for the farmers of Gujarat Farmers will now get electricity even during the day • State Energy Minister Saurabh Patel made this important announcement. Cabinet Minister Saurabh Patel held a press conference and gave important news to the farmers. "Farmers will now get electricity during the day," he said. 17.25 lakh farmers in the state will get electricity on a daily basis. Has announced to provide electricity to farmers during the day.
An important plan has been announced to provide electricity for farming during the day. 17.25 lakh farmers have electricity connection. There was a demand from farmers to provide electricity during the day. PM will inaugurate Kisan Sarvodaya Yojana. 17.25 lakh farmers in the state will get electricity on a daily basis.
The scheme will be completed in two or three years.
Which villages will get electricity for how many hours? The power minister further said that electricity will be provided from 5 am to 9 pm. 11 to 13 thousand mega watts of electricity is required for electricity during the day. Electricity will be provided to 220 villages of Junagadh during the day. Electricity will be provided to 143 villages of Gir Somnath during the day. It will provide electricity to 692 villages of Dahod during the day.
How far is the electricity during the day?
It will take 3 years to set up a structure to provide electricity to farmers on a daily basis. The government has to set up a new structure for Suryodaya Yojana for farmers. In the budget of 2020-21, the Gujarat government has provided Rs.
How far is the electricity during the day? .
It will take 3 years to set up a structure to provide electricity to farmers on a daily basis. The government has to set up a new structure for Kisan Suryodaya Yojana. The Gujarat government has provided Rs. - Rs 3500 crore is to be spent to build the structure in the next 3 years. The government plans to implement the scheme in phases in 3 years.
The government has yet to create a system that can carry electricity.
The government will have to lay 20 new lines. After laying 1 new line of 132 KV transmission, the work will move forward. 233 lines will have to be laid in the state of 66 KV transmission. 17 3817 circuit kilometers will have to be constructed from 254 KV transmission lines.